Sebina Junction - Nata Road Rehabilitation

Pula Consultants in Association with African Consulting Engineers (ACE) has finalized detailed pavement and materials investigations for the rehabilitation of Sebina Junction - Nata Road for Roads Department under the Ministry of Transport and Communications.  The road is 140 Km and basically comprises a variety of treatment to the road section depending of the condition of the road.

In general, 30% of the section called for total Reconstruction for the pavement layers, 30% called to rehabilitation of section which included reprocessing the top layer(base) and topping up with more material to make the base. The remaining 40%  of the road was changing between 25mm asphalt overlay and resealing with single chippings layer.

Client Name: 
Roads Department
Project Group: 
Roads & Traffic Engineering
Industry: 
Infrastructure
Status: 
Completed